MSD will design and construct an anaerobic digestion facility at the Little Miami Wastewater Treatment Plant (WWTP) in the City neighborhoods of Columbia-Tusculum/East End. This facility will process waste solids from the Little Miami, Polk Run, and Sycamore Creek treatment plants on the east side of Hamilton County. The solids are currently being landfilled.
The project team anticipates the following subcontractor packages to be advertised for construction:
Milestone Activity | Milestone Date |
---|---|
Project Introduction Open House | Mid-March 2024 |
Release Packages for Bid | April 18, 2024 |
Bid Proposals Due | May 31, 2024 |
Design-Builder Phase 2 - Notice to Proceed | November 16, 2024 |
Construction Completion | September 3, 2027 |
Substantial Completion | August 11, 2028 |
Final Completion | November 9, 2028 |